MCB Camp Lejeune - Construction Projects Update
Brewster Blvd. Corridor Construction Projects:
| Project Name |
Project Description |
Community Impact |
Projected Date for Completion |
| New Base Entry Road, Ph. 1 |
New four-lane divided highway system from the intersection of Bougainville Drive and Camp Knox Road to the intersection of Brewster Boulevard and Charles Street. The scope of work also includes
widening Brewster Boulevard (to 4 Lanes) from the Charles Street intersection all the way to Holcomb Boulevard, and the realignment of all utilities systems running along Brewster Blvd. The
crossing of Northeast Creek will be facilitated by the construction of a 2000-foot reinforced concrete-deck slab bridge. |
Substantial construction activity on Brewster Blvd: modified vehicle traffic patterns with increased construction trucks and heavy equipment as vehicle lanes are constructed; traffic congestion with
intermittent delays; extended closure of Brewster Blvd bike path and Brewster Blvd closed to pedestrian and bicycle traffic until further notice. |
Spring 2013 |
| Naval Hospital |
109,000 square foot multi-story addition for primary, urgent, and emergency care, pharmacy, and patient administration functions and a 6,700 square foot addition for an MRI area. Site improvements
include new roadways and paved parking. |
Increased construction vehicle traffic and changing traffic patterns on Brewster Blvd as new intersections are constructed |
Winter 2012 |
| PPV Housing |
190 homes off of Brewster Blvd. |
Increased construction vehicle traffic on Brewster Blvd. |
Summer 2012 |
Wallace Creek Regimental Complex Construction Projects:
| Project Name |
Project Description |
Community Impact |
Projected Date for Completion |
| Wallace Creek Regimental Complex Phase II |
12 new major structures: administrative headquarters, operational, maintenance, mission support, and bachelor enlisted quarters. |
Increased construction vehicle traffic near the site |
Summer 2014 |
| WCN BEQ |
Three multi-story, 134-room Bachelor Enlisted Quarters (BEQ), multi-story concrete POV parking garage and armory in the Wallace Creek area. |
Increased construction vehicle traffic near the site |
Winter 2013 |
| ANGLICO & Intel Complexes |
A low-rise building for Intel 197,000 square foot maintenance and operations complex and a multi-story 57,500 square foot HQ building for Air and Naval Gunfire Liaison Company (ANGLICO) and support functions including vehicle maintenance, communications, training and warehouse functions. |
Increased construction vehicle traffic near the site |
Summer 2014 |
Hadnot Point Area Construction Projects:
| Project Name |
Project Description |
Community Impact |
Projected Date for Completion |
| Bachelor Enlisted Quarters |
Three five-story BEQs with 134 two-person rooms. Site work includes the provision for field equipment staging areas, recreation areas, parking areas, sidewalks, signage, and storm water management
retention ponds. |
New routing of Cross Street and redesigned entry to Gottschalk Marina in addition to increased construction traffic in the Hadnot Point area. |
Fall 2012 |
| Hadnot Point Utilities |
Roadway and utility work along the Louis Road corridor from intersection of Piney Green Road and Sneads Ferry Road to intersection of Louis Road and McHugh Boulevard. |
Lane closures and increased construction activity. Plan to start work in January 2012 at Piney Green and Louis then proceed towards McHugh. |
Fall 2013 |
Miscellaneous Construction Projects:
| Project Name |
Project Description |
Community Impact |
Projected Date for Completion |
| Physical Fitness Center |
100,000 square-foot physical fitness facility with an indoor swimming pool. This facility will also serve as a destructive weather shelter. |
Increased construction traffic on Birch Street across from MCX / Commissary Complex. |
Fall 2012 |
| Courthouse Bay ARRA Child Development Center |
34,000 square foot single-story building. Construction will include kitchen and laundry areas, classrooms, and offices. |
Increased construction traffic at the intersection of Marines Road and Sneads Ferry Road. |
Fall 2012 |
| French Creek Utilities |
Roadway and utility work for the extension of Gonzalez Boulevard from McHugh Boulevard to Sneads Ferry Road to include a new bridge, pedestrian pathway, and tank trails. |
Increased construction vehicle traffic in French Creek area |
Fall 2013 |
| Roadwork on Seth Williams Blvd. & McHugh Blvd. |
Patching, resurfacing and installing pavement markings along McHugh Boulevard and Seth Williams Boulevard. |
Lane closures and increased construction activity. Plan to start work at Autumn Oval and work towards Sneads Ferry Rd. |
Spring 2012 |
For more information regarding any of these projects, please contact the Public Affairs Office at (910) 451-7440 or via e-mail at cljn_globe_web@usmc.mil.